Major improvements on way for road in Cambuslang
Published: Tuesday 2 September 2025
Improvement works are to be carried out on a road in Cambuslang from next week.
The works on Hallside Boulevard will see the carriageway resurfaced and lining improvement works taking place across 21 days, subject to favourable weather conditions.
The work will start on Sunday 7 September and is scheduled to be completed at 6pm on Friday 3 October.
The works will be split into five phases:
Phase 1 - Sunday 7 September 2025
- Half of the roundabout at Hallside Boulevard and Village Road
Phase 2 – Monday 8 to Friday 12 September
- Village Road to Elder Crescent (including half of the roundabout at each location)
Phase 3 – Monday 15 to Friday 19 September
- Elder Crescent to Lilac Wynd (including half of the roundabout at each location)
Phase 4 – Monday 22 to Friday 26 September
- Lilac Wynd to Laburnum Avenue (including half of the roundabout at each location)
Phase 5 – Tuesday 30 September to Friday 3 October
- Laburnum Avenue to A724 Hamilton Road (including half of the roundabout at Laburnum Avenue)
Access will be maintained for all residents for the duration of the works, with signed diversions in place for each phase.
Head of Roads, Transportation and Fleet Services, Colin Park, said: “We apologise in advance for any inconvenience these works may cause to road users.
“We would request that all road users allow additional time for all journeys which involve the use of Hallside Boulevard during the times indicated and that they plan their routes accordingly.
“We are sure road users will appreciate the long-term benefits of the improvements when the work has been completed.”
9 October 2026
Poignant way to remember babies gone too soon
9 October 2026
Top marks for Neilsland Primary School
7 October 2026
Second call for Community Council elections in six areas
7 October 2026
Local connections explored through podcasts
6 October 2026
‘Every single foster child leaves a bit of themselves in your heart’
6 October 2026
Community awards highlight volunteering excellence
5 October 2026
Works in Douglas area to be carried out in two phases
5 October 2026
Annual week focuses on challenging poverty
2 October 2026
Learn to generate community wealth from renewable energy developments
2 October 2026
Tree planting commitments highlighted during Climate Week